| 19:22 video @ 12:34 The Wild Story of the Teton Dam Failure The Bureau of Reclamation decided to fill the reservoir even though construction of the primary outlet works would not be done for another year. They did have a secondary outlet works available, but it was not enough to keep the fill rate under a foot (30cm) a day. The dam was built on porous rock and the silt they used in the cutoff trench supported piping. That is, the water was able to erode a pipe through the trench. |
![]() |
| @ 12:59 |
This is the beginning of a sequence of stills that show how this little gurgle quickly grew into a massive breach.
![]() |