Lock #36 via Dennis DeBruler 42.2m (138') x 10.2m (33') x 14.9m (49') "The Kirkfield Lift Lock is the second highest hydraulic lift lock in the world with a lift of 15 metres (49 ft). The lock is situated at the highest point along the Waterway at 256.20 meters (840.5 ft) above sea level." |
Portland Cement In The Trent-Severn Canal Lift Locks
Gord Young, Editor for Lakefield Heritage Research provided the following detailed discussion which explains why the Kirkfield Lift Lock has the trussed steel towers instead of concrete, and the significance of the Portland Cement that was used in the Peterborough Lift Lock.
The Peterborough Lift Lock is the largest and tallest compressed Portland cement structure in the world. We know this, because test walls created at the Lakefield Portland Cement Company's former property have the highest density Portland cement recorded. Kirkfield Lift Lock on the other hand had to substitute a steel cage using the same shape as that at Peterborough, only because Rogers and later, Grant who replaced Rogers, could not get adequate "on-time" deliveries of the Lakefield Portland Cement Company. Something was wrong with the materials coming out of a Portland cement plant that was created near Kirkfield to try to alleviate the problem. Nothing worked for Grant. He threw up his hands and built the steel-caging instead. The design for Peterborough and Kirkfield was based on the Peavey-Haglin grain elevator in St. Paul MN. Only two things changed from the grain elevator to the lift locks. The concrete forms were squared, and, the Portland cement was compressed after being poured. Haglin's grain elevator was a simple Portland pour. Both lift locks and the grain elevator used the same principle of pour a form and then jack-up the form when the lower-half was nearly set. Rogers had a certain amount of Portland cement poured into the form, then had it tamped until it was nearly dry, poured more, tamped, poured more, tamped, then when full, began jacking up the form. Now that the outer slathing-parging has peeled off, you can see the ridges of the pouring forms.
[HistoricBridges]
TalesFromTheAmericanWaterways-3 via Dennis DeBruler From inside the Kirkfield Lift Lock |
|
Rick Stout commented on a post |
KawarthanNow "Ontario Waterway Cruises' Kawartha Voyageur was proceeding through the Kirkfield Lift Lock on September 2, 2022 when the lock experienced a mechanical failure. The lock, which has been closed since then, will reopen on September 26 for limited, single-chamber lockages for vessels returning to their home ports that cannot be trailered. (Photo: Ontario Waterway Cruises / Facebook)" Boaters had to register for a date and time to use the lock. Upbound was six hours and downbound was 30 minutes. (Pumping a high flow against a 15m (49') head must be a challenge.) |
ThePeterboroughExaminer Work to begin to fix Kirkfield Lift Lock at a cost of $7.2 million "On Sept. 2, Lock 36 — the Kirkfield Lift Lock on the Trent Severn Waterway — suffered a mechanical failure, resulting in the site’s closure....“The contractor will arrive at the site in the near future with the goal of having the lift lock fully operational by the beginning of the 2023 navigation season,” states Parks Canada." |
ParksCanada "These single-chamber lockages will operate on demand and are estimated to take approximately 60 minutes. This timing will be finalized upon the final commissioning of a new pump installation. In addition, short delays may be experienced as vessels are grouped for each transfer. Boaters are being requested to remain on their vessels during the transfer and listen carefully to all instructions provided by lock staff." |
NationalParksTraveler Kirkfield Lift Lock Launches Season With Single-Chamber Lockages |
No comments:
Post a Comment